Documents 8 and
9 [PMO file BW 30/43 pages 31 and 32]
Provisional estimate
for the construction of Krematorium IV, drawn up by the civilian employee
Teichmann on 10th March 1944 and signed by the then head of the Auschwitz
Bauleitung. SS Lieutenant Jothann. This estimate was submitted to the
Construction Inspectorate for Silesia and provisionally approved on 26th May
1944.